The tee project is moving along nicely with all of the good weather. At this point, the new white tee on #8 is complete and the new white tees on #5 and #6 are awaiting sod.
Below we are adding sand to the new tee top on #5 white.
The new red tee on #11 is under construction also and will be completed next week.
Below is a before picture of #2 tee complex.
#2 Tee complexes will be tilled, reshaped, laser leveled and the banks will be sodded. The tee top alone will be seeded.