Monday, July 31, 2017

Fireworks Work

Each year the grounds crew spends the week prior to the Independence Day Spectacular setting up for the show.  This year we reduced our future work load by installing pieces of drain tile in the ground next to the bank of the irrigation reservoir.  The drain tile pieces hold the fireworks mortar tubes which in turn hold the mortars.  On the day of the event, fireworks mortars are dropped into the mortar tubes, wired and then fired.  Afterwards, the tubes are cleaned of debris, covered and then sit until next year.  This area will be seeded with a native mix and it will melt into the surrounding landscape.
                
 


Thursday, March 16, 2017

Winter Root Pruning

When tree roots compete with turf tree roots win almost all of the time.  This is especially true when a green is being invaded by roots.  The west side of the putting green and the back of 15 green have been suffering from these invaders over the last couple of years.  So, this winter we installed plastic root barrier panels in both areas.

The panels lock together in a tongue-and-groove fashion creating a continuous barrier.


The picture below shows the putting green ready for the installation of 3 ft tall panels.  


15 grn had very deep roots from the trees between it and Lakeside Rd.  So, there we installed 4 ft tall panels.  




More Irrigation Reservoir Work

Late last fall one of our irrigation pumps was not performing as it should.  The decision was made to repair the pump and the pump was then removed after the new year.

Soon after removing the pump it was realized that leaves being sucked into the pump was the major cause of our pump issues.  The screen at the base of the pump had deteriorated to the point it was letting leaves enter the pump turbines.  The leaves ultimately caused damage to the pump which required repair.



To eliminate the risk of future leaf issues we began investigating potential entry points of leaves into the pumphouse wet-well.  This lead us to emptying the reservoir so we could see the inlet pipe to the wet well.  To our surprise we found holes in our metal inlet pipe, which holds our self cleaning strainer.  The holes were on the bottom portion of the pipe and is probably why we didn't see them last fall when we worked on the strainer.


The short term fix was to use a "tar-like" paste and metal mesh to cover the holes.



The long term fix will most likely come in the form of Cured in Place Pipe.  We will collect quotes on this project and plan to have it done within the next 4-6 years.  

Thursday, December 1, 2016

Irrigation Reservoir Work

Our irrigation system is supplied by water in our reservoir.  As our system runs water sent out onto the course is removed from a large pit in the pumphouse.  The pit is supplied new water by a pipe that runs underground out to the bottom of the reservoir.  At the end of the supply pipe is a self-cleaning strainer.

The self-cleaning strainer keeps fish, leaves and other debris from entering the pumphouse pit.  As the pumps run, water is sent through a 2" supply pipe down to the strainer which then is sprayed out  through a series of nozzles inside of the strainer screen.  The spraying action makes the strainer turn and also removes any debris that may build up on the outside of the screen.

The plumbing for the supply pipe has been an issue in the past and was again this past summer.  The numerous connections were not holding up and blowouts were happening.  We chose to reroute the supply pipe and install a High Density Polyethylene (HDPE) pipe in place of the existing PVC pipe.  The advantage of the HDPE pipe is that it is relatively flexible and can follow the contour of our pond bank down to the strainer, thus reducing the number of connections.  

To do the project we had to remove all of the water from the reservoir, replace the supply pipe and replace any worn parts on the strainer.  Water was then pumped back up to the reservoir via our entrance pump.

 Before.

After.

Tuesday, November 8, 2016

Year End Lunch

Every year the majority of the crew gets laid off in late October/early November.  So, on "layoff day" we go to the casino buffet to celebrate the year.  The time also gives me another opportunity to thank the crew for their hard work and dedication.  While there we feast, gorge ourselves with delicious food and then wonder why we ate so much......

Thanks again guys!!

#9 Green Bank

In the 90's the mounds behind #9 green bank were added and with the addition a few maintenance issues developed over the years.  The green slopes from front to back and as rainwater surface drains down the slope a pool of water always developed on the back right portion of the green after a hard rain.  The pooling was due to the mounds creating a damn effect.

The slope of the mounds were also very steep and were always a challenge to mow.  As the years passed bentgrass began to dominate the bank's surface.  At green or fairway height bentgrass does well but when grown at rough height bentgrass has a tendency to become weakly rooted and "leggy", laying over itself creating mats of turf.  So, as our mowers attempted to mow the bank the poorly rooted turf would rip and peel up leaving unsightly damage.  

Considering the before mentioned issues the Greens Committee decided to make a change.  Over the last 2 weeks the crew and I softened the mounds behind the green, added a drainage inlet off from the collar in the back right and sodded the entire green bank.  The end result is a manageable slope, a well drained green surface and a grass that will hold up to mower traffic.  The area will also play better from a chipping standpoint due to the new grass' consistency.

Below are some before and nearing completion photos.






2016 fw Edge Sodding Project

This fall we continued our fairway edge sodding.  If you remember, 9, 14,15 & 18 fw edges were done last year and have created a nice definition between the fairway and rough.  This year we continued by sodding the fairway edges on 2, 11, 12 & 17.

The staff and I removed the old fairway edge with a big roll sod cutter attached to our tractor.  Dan Kaiser and his crew then laid the new Kentucky Bluegrass sod that we purchased from Red Hen Turf Farm.

Below is a picture of us removing the old fairway edge.